Wednesday, January 20, 2021

Readiness For Concrete Placement in Paint Air Plenum Pit Walls in SouthEastern Michigan -- ANAND Enterprises Project AyoB1J2021

.

I was at the job site to look at the readiness for concrete placement in the pit walls. In the following I present some pictures that I took during my field visit.

Formwork has been installed,  rebars for the peripheral and interior walls were in place, all the appurtenances for the pit walls are in place -- the pit walls are ready for concrete placement.










 

Wednesday, January 13, 2021

Grouting Of Block Walls Confirmatory Investigation For A Project In SouthEastern Michigan -- ANAND Enterprises Project XhuA1J2001

The Building Official had not received a report about grouting of the block walls for this completed project -- so she asked for a report. This happened to be an after the fact situation where I had to provide a confirmatory report that the block walls were indeed grouted during the construction process.

In the following I present some pictures that were taken during the construction phase and then at the end I have presented some pictures of the exterior of the completed project.









Thursday, January 7, 2021

Wood Deck At The Back Of The House And The Kitchen Bump Out Over The Deck -- ANAND Enterprises Project WilJ2J2001

 Following are some pictures of the wood deck at the back of the house with the Kitchen bump out over the deck. The deck and the Kitchen bump out as constructed are structurally sound and will carry all the dead and live loads safely and securely.




















Readiness For Concrete Placement In Paint Air Plenum Pit Base Slab In SouthEastern Michigan -- ANAND Enterprises Project AyoB1J2021

 I was at the job site to look at the readiness for concrete placement in the base slab. In the following I present some pictures that I took during my field visit.

Vapor barrier had been installed,  rebars for the peripheral and interior walls were in place, welded wire fabric for the base slab is in place -- the base slab is ready for concrete placement.








Monday, December 7, 2020

Concrete Placement In Basement ICF Walls -- Addition To Exist House In SouthEastern MI -- ANAND Enterprises Project RedW1J2003

.

 Concrete Placement In Basement ICF Walls

Addition To Existing House

I was at the job site this morning to witness concrete placement . In the following I present some pictures that I took during my field inspection
















Sunday, November 29, 2020

Review Damage To Concrete At Front Entrance of Gas Station From Car Hit-- ANAND Enterprises Project SloW1J2001

.
REVIEW OF DAMAGE TO CONCRETE AT FRONT ENTRANCE
OF THE GAS STATION
IN SOUTHEASTERN MICHIGAN

I visited the project site today to review the alleged damage to concrete at front entrance of the Gas Station that occurred from a car hit.

My objective was to look at such things as 
the extent of the damage
whether the damage occurred from the car hit
or
whether the alleged damage was pre-existing prior to the car hit
and provide a report to my findings to my client

In the following I present some pictures that I took during my field visit








 

Monday, October 19, 2020

Concrete Placement In Footings For New ICF House In SouthEastern Michigan -- ANAND Enterprises Project PluJ1J2001

.
Concrete Placement In Footings of New ICF House In SouthEastern Michigan
Oct-19-2020
I was at the job site this afternoon to witness the concrete placement in the footings.
In the following I present a few pictures that I took during my Field Visit



Sincerely

Yogi Anand, DEng, P.E.