Thursday, January 17, 2019

Getting Ready For Placing Concrete In Wall Above Grade Beam For Building In SouthEastern Michigan -- ANAND Enterprises Project GSK_1J1502

.
I was at the job site this morning to look at the prep work for concrete placement in the wall above the Grade Beam. Also present at the site were Architect Mike Tsakoff, General Contractor Gary Sleiman, and Mike of CTS Foundations to check for general layout, grade elevations, and other site related and Architectural features.

The First Floor open-web top chord bearing steel joists will be fastened to bearing plates that will be anchored to the wall.

I present in the following pictures that I took during my field visit.









No comments:

Post a Comment