Since we are working in a very confined area in the
basement, it took a good deal of planning and
coordination between Miko and his crew and the
ready-mix concrete supply driver to get the concrete
from the alley to the beams in the basement.
The concrete was place in the beams on the East
side farthest away from the alley and then finishing
the day with the beams on the West side.
Miko is going to form the wall piers on Jan-31-2013
and the plans are to place concrete in the wall piers
on Feb-01-2013.