I was at the job site this afternoon to look at the concrete placement in the basement ICF walls. In the following I present some pictures that I took during my field visit. The footings were poured on Dec 14th -- see https://energyefficientbuild.blogspot.com/2023/12/concrete-placemenrt-in-footings-of-new.html
Yes Siree ... building with energy efficiency in mind is very important -- we can not have it as an after thought ... it ought to be the prime consideration right from the planning stage on.
Thursday, December 21, 2023
Thursday, December 14, 2023
Concrete Placemenrt In Footings Of New House with ICF Walls In SouthEastern Michigan -- ANAND Enterprises Project RedW1J2301
I was at the job site this afternoon to look at the concrete placement in the footings of the new house with ICF walls. In the following I present some pictures that I took during my field visit