I was at the job site this afternoon to look at the concrete placement in the basement ICF walls. In the following I present some pictures that I took during my field visit. The footings were poured on Dec 14th -- see https://energyefficientbuild.blogspot.com/2023/12/concrete-placemenrt-in-footings-of-new.html
Thursday, December 21, 2023
Thursday, December 14, 2023
Concrete Placemenrt In Footings Of New House with ICF Walls In SouthEastern Michigan -- ANAND Enterprises Project RedW1J2301
I was at the job site this afternoon to look at the concrete placement in the footings of the new house with ICF walls. In the following I present some pictures that I took during my field visit
Sunday, October 22, 2023
Reviewing Structural Integrity of Existing Walls For Second Story Addition To House In SouthEastern Michigan -- ANAND Enterprises Project OstZ1J2322
I visited the project site today to look at the structural condition of the existing first floor and basement walls for the proposed second story addition.
My walk down inspection of the interior and the exterior of the house indicated that the existing walls can safely support the addition of the second floor to the house.
In the following I present some of the pictures I took during my walk down inspection. If anything unusual is encountered when things are opened up in the field, the Project Manager will be notified promptly who will contact the Architect/Engineer for handling the situation in a satisfactory manner.
Sincerely
Yogi Anand, DEng, P.E.
Subscribe to:
Posts (Atom)